New Artesian Well, Old Road
Conception Harbour, Newfoundland and Labrador
Federal contribution
$38,252
Federal share33%
of $114.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2010201220142016
Built
Approved 6.7 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Conception Harbour
- Construction start
- Aug 3, 2009(actual)
- Construction end
- May 28, 2011(actual)
Against the original forecast
- Construction end14 months lateforecast Mar 31, 2010