Bacon Cove - Armour Stone Placement
Conception Harbour, Newfoundland and Labrador
Federal contribution
$18,103
Federal share33%
of $54.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 6, 2021
2022
Built
Approved 4 weeks before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Conception Harbour
- Construction start
- Sep 4, 2022(actual)
- Construction end
- Sep 14, 2022(actual)
Against the original forecast
- Construction start5 months lateforecast Apr 1, 2022
- Construction end7 weeks earlyforecast Oct 31, 2022
Also in Conception Harbour
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61046 in the federal list. How to read these figures.