Street Upgrading - Highroad South and Chapel Hill

Carbonear, Newfoundland and Labrador

completeHighways and RoadsMRIF
Federal contribution
$157,946
Federal share33%

of $474.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2010201220142016
Built

Approved 6.8 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Carbonear
Construction start
Jun 25, 2009(actual)
Construction end
Jan 27, 2011(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jun 1, 2009
  • Construction end18 months lateforecast Jul 31, 2009

Also in Carbonear

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22787 in the federal list. How to read these figures.