New Deep Well & Pumping System
Petley, Newfoundland and Labrador
Federal contribution
$68,226
Federal share30%
of $229.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2010201220142016
Built
Approved 6.6 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Local Service District of Petley
- Construction start
- Aug 21, 2009(actual)
- Construction end
- Jul 31, 2011(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Oct 1, 2009
- Construction end11 months lateforecast Aug 31, 2010