Water System Improvements - Petley

Petley, Newfoundland and Labrador

completeDrinking WaterRNIS
Federal contribution
$27,066
Federal share33%

of $81.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
2020
Built

Approved 3 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Jun 15, 2020(actual)
Construction end
Nov 30, 2020(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 1, 2020
  • Construction end4 months earlyforecast Mar 31, 2021

Also in Petley

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53993 in the federal list. How to read these figures.