Water Booster System Phase 2
Federal contribution
$162,135
Federal share33%
of $486.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 21, 2009
20102011
Built
Approved 4 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Village of Atholville
- Construction start
- Oct 16, 2009(actual)
- Construction end
- Mar 1, 2011(actual)
Against the original forecast
- Construction start7 months lateforecast Apr 1, 2009
- Construction end2.4 years earlyforecast Jul 31, 2013