Line replacement and separation, Ferguson and Parkside Roads

Atholville, New Brunswick

completeDrinking WaterCWWF
Federal contribution
$452,496
Federal share50%

of $905.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 18, 2016
201720182019
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Atholville
Construction start
Jun 20, 2017(actual)
Construction end
Aug 23, 2019(actual)

Against the original forecast

  • Construction start7 weeks lateforecast May 1, 2017
  • Construction end10 months lateforecast Oct 31, 2018