Schedule
Announced and approvedAug 18, 2016
201720182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Atholville
- Construction start
- Jun 20, 2017(actual)
- Construction end
- Aug 23, 2019(actual)
Against the original forecast
- Construction start7 weeks lateforecast May 1, 2017
- Construction end10 months lateforecast Oct 31, 2018