Reidville Road Upgrading
Reidville, Newfoundland and Labrador
Federal contribution
$112,610
Federal share29%
of $382.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2010201220142016
Built
Approved 6.7 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Reidville
- Construction start
- Aug 3, 2009(actual)
- Construction end
- Aug 16, 2010(actual)
Against the original forecast
- Construction start8 months earlyforecast Apr 3, 2010
- Construction end8 weeks earlyforecast Oct 9, 2010
Also in Reidville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22860 in the federal list. How to read these figures.