Upgrade and Pave Old Rocky Brook Road
Reidville, Newfoundland and Labrador
Federal contribution
$185,982
Federal share33%
of $557.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2024
20232024
Built
Approved 19 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Town of Reidville
- Construction start
- Oct 9, 2023(actual)
- Construction end
- Nov 6, 2023(actual)
Against the original forecast
- Construction start3 months lateforecast Jul 1, 2023
- Construction end3 weeks earlyforecast Nov 30, 2023
Also in Reidville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65071 in the federal list. How to read these figures.