$550,540
Federal share33%

of $1.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 12, 2009
2010
Built

Approved 3 weeks before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
Village of Minto
Construction start
Jun 14, 2010(actual)
Construction end
Oct 6, 2010(actual)

Against the original forecast

  • Construction start7 months lateforecast Nov 1, 2009
  • Construction end6 months earlyforecast Mar 31, 2011