Back to projects

Sanitary and Storm Sewer Replacement and Upgrades

Minto, New Brunswick

completeWastewaterCWWF
Federal contribution
$391,171
Federal share50%

of $783.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 18, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Minto
Construction start
Jul 4, 2017(actual)
Construction end
Oct 5, 2018(actual)

Against the original forecast

  • Construction start2 months lateforecast May 1, 2017
  • Construction end4 weeks earlyforecast Oct 31, 2018

Also in Minto

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47313 in the federal list. How to read these figures.