Sanitary and Storm Sewer Replacement and Upgrades
Federal contribution
$391,171
Federal share50%
of $783.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 18, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Minto
- Construction start
- Jul 4, 2017(actual)
- Construction end
- Oct 5, 2018(actual)
Against the original forecast
- Construction start2 months lateforecast May 1, 2017
- Construction end4 weeks earlyforecast Oct 31, 2018
Also in Minto