Back to projects

Installation of North Bay Water Meters

North Bay, Ontario

completeDrinking WaterCC
Federal contribution
$2.2M
$2,226,574
Federal share33%

of $6.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2009201120132015
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
City of North Bay
Construction start
Jan 8, 2013(actual)
Construction end
Mar 31, 2016(actual)

Also in North Bay