Algonquin/Front Rehabiliation Program
Federal contribution
$4.7M
$4,666,667
Federal share33%
of $14.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of North Bay
- Construction start
- Aug 12, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jul 13, 2009
- Construction end4 weeks lateforecast Sep 30, 2011
Also in North Bay
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32334 in the federal list. How to read these figures.