HVAC Upgrades and Bottle Water Filling Stations

North Bay, Ontario

completeVentilationCVRIS
Federal contribution
$3.6M
$3,640,470
Federal share80%

of $4.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2021
202220232024
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Mar 29, 2021(actual)
Construction end
Dec 31, 2023(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Feb 19, 2021

Also in North Bay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58641 in the federal list. How to read these figures.