Replacement of Butler Creek Bridge
Federal contribution
$1.3M
$1,292,589
Federal share45%
of $2.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2009201120132015
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Moosonee
- Construction start
- Nov 30, 2009(actual)
- Construction end
- Jul 2, 2015(actual)
Against the original forecast
- Construction start5 months lateforecast Jul 15, 2009
- Construction end18 months earlyforecast Dec 31, 2016
Also in Moosonee
- School Ventilation and Building Controls$2.5M
- Upgrade of Watermain on Bay Road, Wabun Road and Revillon Road$2.0M
- Second Street and Bay Road Sanitary Sewer, Watermain, and Storm Drainage Reconstruction$798.2K
- Mistik/Meechim - Water / Wastewater Line Replacement$720.3K
- Water Treatment Plant Repairs / Improvements$183.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22940 in the federal list. How to read these figures.