Upgrade of Watermain on Bay Road, Wabun Road and Revillon Road

Moosonee, Ontario

underwayDrinking WaterGIS
Federal contribution
$2.0M
$1,999,997
Federal share40%

of $5.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2022
today
20232024202520262027
BuiltForecast

Approved 3 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Moosonee
Construction start
Aug 25, 2022(actual)
Construction end
Oct 30, 2026(forecast)

Also in Moosonee

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 62949 in the federal list. How to read these figures.