Construction of the Hanover Regional Recreation Complex
Federal contribution
$3.5M
$3,467,212
Federal share33%
of $10.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Hanover
- Construction start
- Jul 15, 2009(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction end8 months lateforecast Jul 30, 2010
Also in Hanover
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 22951 in the federal list. How to read these figures.