Replacement of 7th Avenue Water Tower
Federal contribution
$2.0M
$2,000,000
Federal share40%
of $5.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2022
today
20232024202520262027
BuiltForecast
Approved 3 weeks before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Hanover
- Construction start
- Mar 17, 2025(actual)
- Construction end
- Oct 30, 2026(forecast)
Also in Hanover