Water and Sewer Upgrade – Three Streets

Norris Point, Newfoundland and Labrador

completeDrinking WaterMRIF
Federal contribution
$108,896
Federal share28%

of $382.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2010201220142016
Built

Approved 6.9 years before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Norris Point
Construction start
Aug 12, 2010(actual)
Construction end
Nov 20, 2010(actual)

Against the original forecast

  • Construction start14 months lateforecast Jun 1, 2009
  • Construction end12 months lateforecast Nov 30, 2009