Main Street Watermain Upgrade
Norris Point, Newfoundland and Labrador
Federal contribution
$460,621
Federal share44%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
20172018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Norris Point
- Construction start
- Jul 18, 2017(actual)
- Construction end
- Jun 29, 2018(actual)
Against the original forecast
- Construction end4 months earlyforecast Oct 24, 2018
Also in Norris Point
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47039 in the federal list. How to read these figures.