Upgrading of Wastewater Treatment Plant

Charlo, New Brunswick

completeWastewaterCC
Federal contribution
$801,831
Federal share33%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 21, 2009
201020112012
Built

Approved 4 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
Village of Charlo
Construction start
Jun 13, 2011(actual)
Construction end
May 29, 2012(actual)

Against the original forecast

  • Construction start14 months lateforecast Apr 1, 2010
  • Construction end2 months earlyforecast Jul 31, 2012