Water Distribution and Sanitary Sewer System Upgrades
Federal contribution
$575,339
Federal share49%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 20, 2017
2017201820192020
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Charlo
- Construction start
- Jun 12, 2017(actual)
- Construction end
- Sep 30, 2020(actual)
Against the original forecast
- Construction start6 weeks lateforecast May 1, 2017
- Construction end10 months lateforecast Nov 30, 2019
Also in Charlo