Back to projects

Water Distribution and Sanitary Sewer System Upgrades

Charlo, New Brunswick

completeDrinking WaterCWWF
Federal contribution
$575,339
Federal share49%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2017
2017201820192020
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Charlo
Construction start
Jun 12, 2017(actual)
Construction end
Sep 30, 2020(actual)

Against the original forecast

  • Construction start6 weeks lateforecast May 1, 2017
  • Construction end10 months lateforecast Nov 30, 2019