Replacement of Barbers Bay Bridge
Federal contribution
$1.7M
$1,654,771
Federal share33%
of $5.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Timmins
- Construction start
- Jun 15, 2009(actual)
- Construction end
- May 31, 2011(actual)
Against the original forecast
- Construction end10 months lateforecast Jul 30, 2010
Also in Timmins
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23092 in the federal list. How to read these figures.