Building improvements to address air quality and transmission risks at various locations
Federal contribution
$2.1M
$2,108,947
Federal share80%
of $2.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 14, 2021
202220232024
Built
Approved 8 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Conseil Scolaire Catholique de District des Grandes-Rivieres
- Construction start
- Jun 1, 2021(actual)
- Construction end
- Dec 31, 2023(actual)
Against the original forecast
- Construction start3 months lateforecast Feb 18, 2021
Also in Timmins
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58524 in the federal list. How to read these figures.