Revitalization of Hanes Road
Federal contribution
$941,005
Federal share33%
of $2.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Huntsville
- Construction start
- Jun 1, 2009(actual)
- Construction end
- Sep 11, 2010(actual)
Against the original forecast
- Construction end4 months lateforecast May 1, 2010
Also in Huntsville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23111 in the federal list. How to read these figures.