Reconstruction of Deerhurst Drive
Federal contribution
$2.0M
$1,989,156
Federal share67%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 25, 2009
ApprovedOct 21, 2009
Built
Approved 4 months after the announcement.
- Program
- G8 Legacy Fund
- Ultimate recipient
- Corporation of the Town of Huntsville
- Construction start
- Mar 20, 2009(actual)
- Construction end
- Jul 1, 2009(actual)
Also in Huntsville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 33197 in the federal list. How to read these figures.