Improvements to the Sydenham Water Treatment Facility
Federal contribution
$473,333
Federal share33%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Township of South Frontenac
- Construction start
- Aug 12, 2010(actual)
- Construction end
- Apr 24, 2011(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Sep 22, 2010
- Construction end8 weeks lateforecast Mar 1, 2011