Back to projects

Improvements to the Sydenham Water Treatment Facility

Sydenham, Ontario

completeDrinking WaterCC
Federal contribution
$473,333
Federal share33%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
20102011
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Township of South Frontenac
Construction start
Aug 12, 2010(actual)
Construction end
Apr 24, 2011(actual)

Against the original forecast

  • Construction start6 weeks earlyforecast Sep 22, 2010
  • Construction end8 weeks lateforecast Mar 1, 2011

Also in Sydenham

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23114 in the federal list. How to read these figures.