Ambulance station - Township of South Frontenac
Federal contribution
$250,000
Federal share33%
of $750.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- County of Frontenac
- Construction start
- May 15, 2010(actual)
- Construction end
- Jan 19, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Mar 15, 2010
- Construction end5 weeks lateforecast Dec 15, 2010
Also in Sydenham
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32363 in the federal list. How to read these figures.