Back to projects

Rea Bridge Replacement

Guelph, Ontario

completeHighways and RoadsCC
Federal contribution
$517,377
Federal share33%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2010
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
County of Wellington
Construction start
Aug 1, 2009(actual)
Construction end
Oct 31, 2010(actual)

Against the original forecast

  • Construction end4 months lateforecast Jun 30, 2010