Reconstruction of Post Street

Whitney, Ontario

completeHighways and RoadsCC
Federal contribution
$186,226
Federal share33%

of $558.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2010
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Township of South Algonquin
Construction start
Jul 13, 2010(actual)
Construction end
Aug 1, 2010(actual)

Against the original forecast

  • Construction start12 months lateforecast Jul 13, 2009
  • Construction end2 months lateforecast Jun 1, 2010

Also in Whitney

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23131 in the federal list. How to read these figures.