Reconstruction of Lake Street
Federal contribution
$166,667
Federal share33%
of $500.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Township of South Algonquin
- Construction start
- Sep 17, 2009(actual)
- Construction end
- Nov 1, 2009(actual)
Against the original forecast
- Construction end14 months earlyforecast Dec 31, 2010