Reconstruction of Concession Street - Quarterline Road

Tillsonburg, Ontario

completeHighways and RoadsCC
Federal contribution
$515,824
Federal share33%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
20102011
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Tillsonburg
Construction start
Aug 24, 2009(actual)
Construction end
Sep 30, 2011(actual)

Against the original forecast

  • Construction start5 months lateforecast Apr 1, 2009
  • Construction end8 months earlyforecast May 31, 2012