Tillsonburg Community Centre Rehabilitation

Tillsonburg, Ontario

completeRecreationCCRIS
Federal contribution
$2.0M
$1,999,801
Federal share40%

of $5.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 6, 2021
2022202320242025
Built

Approved 4 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Town of Tillsonburg
Construction start
Apr 15, 2022(actual)
Construction end
Feb 28, 2025(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Jan 31, 2025

Also in Tillsonburg

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58171 in the federal list. How to read these figures.