Upgrades to the Eganville Water Treatment Plant and Universal Water Meter Installation

Eganville, Ontario

completeDrinking WaterCC
Federal contribution
$300,000
Federal share33%

of $900.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
20102011
Built
Program
Building Canada Fund - Communities Component
Construction start
Jun 10, 2009(actual)
Construction end
Mar 17, 2011(actual)

Against the original forecast

  • Construction end3 months lateforecast Dec 10, 2010

Also in Eganville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23177 in the federal list. How to read these figures.