Alice Street Rehabilitation
Federal contribution
$273,408
Federal share33%
of $825.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Bonnechere Valley
- Construction start
- Aug 4, 2009(actual)
- Construction end
- Nov 20, 2009(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jul 15, 2009
- Construction end3 weeks lateforecast Oct 31, 2009
Also in Eganville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32608 in the federal list. How to read these figures.