Alice Street Rehabilitation

Eganville, Ontario

completeHighways and RoadsISF
Federal contribution
$273,408
Federal share33%

of $825.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Aug 4, 2009(actual)
Construction end
Nov 20, 2009(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jul 15, 2009
  • Construction end3 weeks lateforecast Oct 31, 2009