Reclamation of the St.-Charles Landfill
Federal contribution
$141,228
Federal share25%
of $562.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
20092011201320152017
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Municipality of St. Charles
- Construction start
- Jun 1, 2009(actual)
- Construction end
- Dec 31, 2016(actual)
Against the original forecast
- Construction start5.8 years earlyforecast Apr 1, 2015
- Construction end9 months lateforecast Mar 31, 2016
Also in St. Charles
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23930 in the federal list. How to read these figures.