Musky Bay Road Realignment
Federal contribution
$236,759
Federal share33%
of $711.7K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of St. Charles
- Construction start
- Aug 15, 2009(actual)
- Construction end
- Nov 29, 2010(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 15, 2009
- Construction end4 weeks lateforecast Oct 29, 2010
Also in St. Charles
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 30600 in the federal list. How to read these figures.