Improvements to 57th Street and Shore Lane Drainage

Wasaga Beach, Ontario

completeWastewaterCC
Federal contribution
$900,073
Federal share33%

of $2.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2010
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Wasaga Beach
Construction start
Sep 30, 2009(actual)
Construction end
Jul 28, 2010(actual)

Against the original forecast

  • Construction end11 months earlyforecast Jun 30, 2011