Back to projects

Renovation of Wasaga Beach Fire Station 2

Wasaga Beach, Ontario

completeVentilationCVRIS
Federal contribution
$289,253
Federal share80%

of $361.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 29, 2021
20222023
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Town of Wasaga Beach
Construction start
Jul 11, 2022(actual)
Construction end
May 1, 2023(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jun 1, 2022
  • Construction end2 months earlyforecast Jun 30, 2023

Also in Wasaga Beach

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59730 in the federal list. How to read these figures.