Replacement of the Glasgow Bridge
Federal contribution
$275,000
Federal share33%
of $825.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Township of Uxbridge
- Construction start
- Jul 19, 2010(actual)
- Construction end
- Nov 12, 2010(actual)
Against the original forecast
- Construction start14 months lateforecast Jun 1, 2009
- Construction end6 weeks lateforecast Sep 30, 2010
Also in Uxbridge
- Brock Street Culvert$2.5M
- Pickering Uxbridge Broadband Fibre Optic Trunk$2.3M
- Road Rehabilitation - Regional Highway 47$1.7M
- Rehabilitation and Upgrade of the Forsythe West Stormwater Management Facility$945.9K
- Rehabilitation of Barton Farm Stormwater Management Pond (Sediment Removal and Disposal)$190.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23936 in the federal list. How to read these figures.