Rehabilitation of Barton Farm Stormwater Management Pond (Sediment Removal and Disposal)

Uxbridge, Ontario

completeWastewaterCWWF
Federal contribution
$190,017
Federal share37%

of $512.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 28, 2017
2018
Built

Approved 8 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Jul 1, 2017(actual)
Construction end
Jul 31, 2018(actual)

Against the original forecast

  • Construction end7 months lateforecast Dec 31, 2017