Rehabilitation of Barton Farm Stormwater Management Pond (Sediment Removal and Disposal)
Federal contribution
$190,017
Federal share37%
of $512.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 28, 2017
2018
Built
Approved 8 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Corporation of the Township of Uxbridge
- Construction start
- Jul 1, 2017(actual)
- Construction end
- Jul 31, 2018(actual)
Against the original forecast
- Construction end7 months lateforecast Dec 31, 2017