Rehabilitation of Factory Creek Bridge
Federal contribution
$330,319
Federal share33%
of $991.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- County of Northumberland
- Construction start
- Aug 7, 2009(actual)
- Construction end
- Nov 18, 2010(actual)
Against the original forecast
- Construction end6 months lateforecast May 31, 2010
Also in Cobourg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 23937 in the federal list. How to read these figures.