Back to projects

Construction of the Fenelon Falls Recreation Complex

Lindsay, Ontario

completeRecreationCC
Federal contribution
$3.3M
$3,262,362
Federal share33%

of $9.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2009201120132015
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Kawartha Lakes
Construction start
Apr 1, 2009(actual)
Construction end
Mar 31, 2016(actual)

Also in Lindsay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24554 in the federal list. How to read these figures.