Back to projects

Rehabilitation of CKL Road 45

Lindsay, Ontario

completeHighways and RoadsCC Top Up
Federal contribution
$1.2M
$1,188,852
Federal share33%

of $3.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
2010
Built
Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
City of Kawartha Lakes
Construction start
Aug 10, 2009(actual)
Construction end
Sep 30, 2010(actual)

Also in Lindsay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27869 in the federal list. How to read these figures.