Installation of Ultraviolet Treatment Units
Federal contribution
$127,710
Federal share45%
of $283.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2009201120132015
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Local Services Board of Redditt
- Construction start
- Sep 20, 2013(actual)
- Construction end
- Nov 15, 2015(actual)
Against the original forecast
- Construction start3.5 years lateforecast Apr 1, 2010
- Construction end2 weeks earlyforecast Nov 30, 2015
Also in Redditt
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24560 in the federal list. How to read these figures.