Installation of Water Purification Systems

Redditt, Ontario

completeDrinking WaterCC Top Up
Federal contribution
$121,050
Federal share45%

of $269.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 5, 2009
20102011
Built
Program
Building Canada Fund - Communities Component Top Up
Construction start
Sep 20, 2010(actual)
Construction end
Feb 28, 2011(actual)

Also in Redditt

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27841 in the federal list. How to read these figures.