Rehabilitation of the Sanitary and Storm Sewer
Federal contribution
$1.4M
$1,389,570
Federal share30%
of $4.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2009201120132015
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Belleville
- Construction start
- Jun 1, 2009(actual)
- Construction end
- Dec 31, 2015(actual)
Against the original forecast
- Construction end3 years lateforecast Dec 31, 2012
Also in Belleville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24562 in the federal list. How to read these figures.