Construction of the Sauble Beach Sewage Treatment Plant

Wiarton, Ontario

completeWastewaterCC
Federal contribution
$2.1M
$2,083,334
Federal share33%

of $6.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2009
2009201120132015
Built
Program
Building Canada Fund - Communities Component
Construction start
Jan 1, 2015(actual)
Construction end
Mar 31, 2016(actual)

Also in Wiarton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24580 in the federal list. How to read these figures.