Bluewater Park Rehabilitation

Wiarton, Ontario

completeRecreationISF
Federal contribution
$453,582
Federal share32%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jul 10, 2010(actual)
Construction end
Jul 22, 2011(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Jun 25, 2010
  • Construction end3 months earlyforecast Oct 28, 2011