Reconstruction of Monk Street
Federal contribution
$607,777
Federal share33%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Township of Chapleau
- Construction start
- May 25, 2009(actual)
- Construction end
- Dec 15, 2010(actual)
Against the original forecast
- Construction end2 weeks earlyforecast Dec 31, 2010
Also in Chapleau
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24614 in the federal list. How to read these figures.